  Secretary of the Navy (SECNAV), the Honorable Donald C. Winter discusses the Littoral Combat Ship (LCS) acquisition program during a press conference in the Pentagon.
070315-N-3642E-063 WASHINGTON (March 15, 2007) - Secretary of the Navy (SECNAV), the Honorable Donald C. Winter discusses the Littoral Combat Ship (LCS) acquisition program during a press conference in the Pentagon. The new program plan will improve management oversight, implement more strict cost controls, incorporate selective contract restructuring and ensure vital warfighting capability is provided to the fleet in a timely manner. U.S. Navy photo by Chief Mass Communication Specialist Shawn P. Eklund (RELEASED)
 
View Larger Download HiRes
 

Navy Terminates Littoral Combat Ship 3
Story Number: NNS070413-06
Release Date: 4/13/2007 12:28:00 PM
Top News Story - Editors should consider using these stories first in local publications.

From the Office of the Assistant Secretary of Defense Public Affairs

WASHINGTON (NNS) -- Secretary of the Navy Donald C. Winter announced April 12 that the Department of the Navy is terminating construction of the third Littoral Combat Ship (LCS 3) for convenience under the termination clause of the contract because the Navy and Lockheed Martin could not reach agreement on the terms of a modified contract.

The Navy issued a stop-work order on construction on LCS 3 in January following a series of cost overruns on LCS 1 and projection of cost increases on LCS 3, which are being built by Lockheed Martin under a cost-plus contract.

The Navy announced in March that it would consider lifting the stop-work order on LCS 3 if the Navy and Lockheed Martin could agree on the terms for a fixed price incentive agreement by mid-April. The Navy worked closely with Lockheed Martin to try to restructure the agreement for LCS 3 to more equitably balance cost and risk, but could not come to terms and conditions that were acceptable to both parties.

The Navy remains committed to completing construction on LCS 1 under the current contract with Lockheed Martin. LCS 2 and 4 are under contract with General Dynamics, and the Navy will monitor their cost performance closely. The Navy intends to continue with the plan to assess costs and capabilities of LCS 1 and LCS 2 and transition to a single seaframe configuration in fiscal year 2010 after an operational assessment and considering all relevant factors. General Dynamics’ ships will continue on a cost-plus basis as long as its costs remain defined and manageable. If the cost performance becomes unacceptable, then General Dynamics will be subject to similar restructuring requirements.

“LCS continues to be a critical warfighting requirement for our Navy to maintain dominance in the littorals and strategic choke points around the world,” said Winter. “While this is a difficult decision, we recognize that active oversight and strict cost controls in the early years are necessary to ensuring we can deliver these ships to the fleet over the long term.”

For more news from around the fleet, visit www.navy.mil.

E-mail this story to a friend | Send a comment about this story

Related Stories:
Navy Terminates Fourth Littoral Combat Ship  - 11/1/2007 High Interest Story Watch Video
Secretary of the Navy Recommends Way Ahead for LCS Program - 3/15/2007 High Interest Story This Story has a Photo
DoN Budget Request for FY08 Addresses Near and Long-term Needs - 3/1/2007 High Interest Story This Story has a Photo


MS Word Friendly

Print Friendly


Subscribe NavNews

Submit Story/Photos

Tools

Contact Us

Privacy & Security

About This Site

External Links

Home